Progress payments: the two-minute check

Everyone asks about the deposit. Few people read the payment schedule, and that is where jobs go wrong: a lawful deposit followed by oversized "progress" payments leaves your money far ahead of the work.

Rule 1: the schedule must be specific

If a home improvement contract has payments before the work is complete, it must include a "Schedule of Progress Payments." Each payment must be stated in dollars and cents and say what work, services, materials and equipment it covers (BPC 7159(d)(9), 7159.5(a)(4)). The contract must also carry this statement in bold type:

"The schedule of progress payments must specifically describe each phase of work, including the type and amount of work or services scheduled to be supplied in each phase, along with the amount of each proposed progress payment. IT IS AGAINST THE LAW FOR A CONTRACTOR TO COLLECT PAYMENT FOR WORK NOT YET COMPLETED, OR FOR MATERIALS NOT YET DELIVERED. HOWEVER, A CONTRACTOR MAY REQUIRE A DOWNPAYMENT."

A schedule that says "50% at start, 40% midway, 10% at the end" falls short twice: percentages instead of dollars, and no described phases.

Rule 2: payments may never exceed the value delivered

Apart from the down payment ($1,000 or 10% of the price, whichever is less), a contractor "shall neither request nor accept payment that exceeds the value of the work performed or material delivered" (BPC 7159.5(a)(5)). Breaking that rule is a misdemeanor, with a fine of up to $5,000, up to a year in county jail, or both (7159.5(b)(1)).

Note "material delivered." Cabinets sitting in your garage are value a payment can cover. "Half up front for materials" that have not been ordered, let alone delivered, is the opposite.

The check

Read the schedule one line at a time and ask after each payment: if the contractor disappeared the morning after this payment cleared, would I have paid only for what is now at my house?

A $40,000 kitchen, in the shape that fails:

The same kitchen, in a shape that passes:

Every line is a described phase, in dollars, paid after the value exists.

Two things that change the picture

Keep a real final payment, large enough that finishing the punch list is worth the contractor's trip back.

Check your payment schedule, free

Paste the quote or contract. We read each payment in the schedule and point out any that come before the work they pay for, a down payment above the limit, and a schedule that does not add up to the price, along with the contractor's live CSLB record. No account is needed. Already signed and paying? Project Guard ($39 once for one project, 90 days, no renewal, refundable any time in those 90 days) checks each payment before you make it.

Check a quote or contract

General information about California law, not legal advice. Checked against the official text on November 3, 2026. Sources: BPC 7159, BPC 7159.5, CSLB home improvement contracts guide.